NEW QUESTION # 191
Which one of the following statements best defines the purpose of a Product Breakdown Structure (PBS)?
- A. To define the hierarchy of deliverables that are required to be produced on the project.
- B. To define how the products are produced by identifying derivations and dependencies.
- C. To establish the extent of work required prior to project commissioning and the handover.
- D. To identify the health and safety strategies and procedures to be used on the project.
Answer: C
NEW QUESTION # 192
The primary purpose of a product breakdown structure (PBS) is to:
- A. define precisely what resources will be used on the project.
- B. detail all the products in order of priority.
- C. define all the products that the project will produce.
- D. map out the key project elements identified in the business plan
Answer: C
NEW QUESTION # 193
Which one of the following best describes the entire project reporting process?
- A. Publicising the project benefits to the business organisation.
- B. Notifying team members of the project's progress at the weekly team meeting.
- C. Formally notifying the status of the project to the project's stakeholders.
- D. Producing an exception report to communicate A. project issue to the project board.
Answer: C
NEW QUESTION # 194
Which one of the following is least likely to be a success criteria?
- A. A target for the project to receive zero change requests.
- B. The date by which the project is to be completed.
- C. Delivery of products that meet required specifications.
- D. The awarding of bonuses to senior management.
Answer: D
NEW QUESTION # 195
Cost Breakdown Structure (CBS) shows costs assigned to:
- A. individual resources using the Work Breakdown Structure (WBS).
- B. individual work packages using the Work Breakdown Structure (WBS).
- C. individual deliverables using the Responsibility Assignment Matrix (RAM)
- D. individual resources using the Responsibility Assignment Matrix (RAM).
Answer: B
NEW QUESTION # 196
When managing the internal context, the project manager should especially be aware of:
- A. organisational strategy, policies and frameworks.
- B. competitive positioning.
- C. new legislation.
Answer: A
Explanation:
D business continuity.
NEW QUESTION # 197
Which one of the following statements is true?
- A. An increase in project scope is likely to increase project cost.
- B. An increase in the project quality requirements is likely to decrease project cost.
- C. A decrease in the project cost is likely to decrease project time.
- D. A decrease in the project time is likely to increase project quality.
Answer: A
NEW QUESTION # 198
The value of a risk log lies in its ability to provide:
- A. A. means of assessing the likelihood and impact of risks.
- B. A. structured process for risk management.
- C. A. record of all risks, their impact and the actions taken to manage them.
- D. A. record of the ownership of risk and issue management actions.
Answer: C
NEW QUESTION # 199
A project is typically defined in terms of scope, time, cost and which other parameter?
- A. Benefits.
- B. Tolerance.
- C. Controls.
- D. Quality.
Answer: C
NEW QUESTION # 200
The prime purpose of configuration management is to:
- A. ensure the traceability and integrity of the delivered product or products
- B. maximise the impact of agreed enhancements to the project deliverables
- C. minimise the impact of changes on the scope of the project
- D. ensure that the final product meets the needs of the business as defined by key stakeholders.
Answer: A
NEW QUESTION # 201
Which one of the following does not describe the prime purpose of the business case?
- A. To describe the operational impact of project delivery.
- B. To document the benefits of the various options that have been considered.
- C. To show how the project tasks will be scheduled to achieve success criteria.
- D. To define the strategic direction for the project.
Answer: C
NEW QUESTION # 202
Project reporting can best be defined as:
- A. informing stakeholders about the project.
- B. gathering stakeholder feedback.
- C. collecting project information.
- D. storing and archiving of project information.
Answer: A
NEW QUESTION # 203
What action is essential after a change has been approved?
- A. The actual impact of the change is assessed.
- B. The next change requested should be reviewed as quickly as possible.
- C. The related plans must be updated to reflect the change.
- D. The highlights of the change are communicated directly to the sponsor.
Answer: C
NEW QUESTION # 204
What aspect of business case development will assist project management the most?
- A. That the business case has sufficient detail to allow the project manager to take over accountability for the financial success of the project
- B. That the project management plan for the project is captured as an appendix of the approved business case.
- C. That the sponsor who has developed the business case will also be the sponsor who oversees actual delivery of the project.
- D. That the option chosen has taken recognition of how the resultant project is actually going to be managed and delivered.
Answer: D
NEW QUESTION # 205
Which Of the following might be a probable cause to consider early project closure?
- A. The is expected to yield greater value than stated in the business
- B. The project manager has resigned and an immediate replacement is unavailable
- C. The project is on schedule but spent less than expected
- D. The cost to complete the project is greater than the value to be achieved.
Answer: D
NEW QUESTION # 206
A typical risk management process would follow the steps:
- A. assessment, analysis. closure. response.
- B. identification. analysis, response. closure.
- C. identification, planning, response. closure
- D. assessment, planning, managing. response.
Answer: B
NEW QUESTION # 207
Which one of the following is not considered in resource management?
- A. Influencing resources.
- B. Assigning resources to activities.
- C. Matching resources to the schedule.
- D. Identifying resources.
Answer: A
NEW QUESTION # 208
......
Pass Your Project Fundamentals Qualification APM-PFQ Exam on Oct 31, 2025 with 408 Questions: https://www.exam4free.com/APM-PFQ-valid-dumps.html