[2026] Use Valid New Free C-P2W22-2504 Exam Dumps Answers C-P2W22-2504 Braindumps PDF, SAP C-P2W22-2504 Exam Cram NEW QUESTION # 24 Which of the following processes lead to an indicator in the planning file?Note: There are 2 correct answers to this question. A. Changing a storage bin B. Changing an operation time C. Changing a dependent requirement D. Changing a delivery address Answer: B,C NEW QUESTION [...]

[2026] Use Valid New Free C-P2W22-2504 Exam Dumps & Answers [Q24-Q42]

Share

[2026] Use Valid New Free C-P2W22-2504 Exam Dumps & Answers

C-P2W22-2504 Braindumps PDF, SAP C-P2W22-2504 Exam Cram

NEW QUESTION # 24
Which of the following processes lead to an indicator in the planning file?
Note: There are 2 correct answers to this question.

  • A. Changing a storage bin
  • B. Changing an operation time
  • C. Changing a dependent requirement
  • D. Changing a delivery address

Answer: B,C


NEW QUESTION # 25
Which of the following are replenishment strategies for Kanban containers?
Note: There are 2 correct answers to this question.

  • A. Replenishment using planned independent requirements
  • B. Replenishment using direct transfer posting
  • C. Replenishment using reservations
  • D. Replenishment using process orders

Answer: B,C


NEW QUESTION # 26
What will happen in the MRP run if you have created a new MRP-relevant material that supports both in-house production and external procurement?

  • A. The MRP run starts with external procurement.
  • B. The MRP run starts with in-house production.
  • C. The MRP run plans the material only if a quotation has been maintained.
  • D. The MRP run does NOT consider the material; it has to be planned interactively.

Answer: B


NEW QUESTION # 27
How do you assign resources in a master recipe with operations and phases?

  • A. You assign resources to the sub-operations.
  • B. You assign resources to the operations.
  • C. You assign resources to the header of the master recipe.
  • D. You assign resources to the phases.

Answer: B


NEW QUESTION # 28
In which master data objects do you maintain data to determine the duration of an operation for production?
Note: There are 2 correct answers to this question.

  • A. Production version
  • B. Material master
  • C. Routing
  • D. Work center

Answer: C,D


NEW QUESTION # 29
What are the possible results of a production planning run in Advanced Planning (PP/DS)?
Note: There are 2 correct answers to this question.

  • A. Planned order
  • B. Production order
  • C. Scheduling agreement schedule line
  • D. Purchase order

Answer: A,C


NEW QUESTION # 30
How are dependent requirements for assemblies created?
Note: There are 2 correct answers to this question.

  • A. They are created together with the independent requirement for the finished product.
  • B. They are created with exact times in Advanced Planning.
  • C. They are only created for multilevel bill of material (BOM) structures.
  • D. They are created on the assembly level during the planning run.

Answer: B,D


NEW QUESTION # 31
When working with the material status, for which business areas can you set a warning message?
Note: There are 2 correct answers to this question.

  • A. Purchasing
  • B. Sales
  • C. Classification
  • D. Plant Maintenance

Answer: B,D


NEW QUESTION # 32
Which settings can you make in a production scheduling profile?
Note: There are 3 correct answers to this question.

  • A. Automatic goods issue on confirmation
  • B. Default order types
  • C. Automatic release on order creation
  • D. Automatic goods receipt on confirmation
  • E. Automatic print on order creation

Answer: B,C,D


NEW QUESTION # 33
Which of the following are scheduling time elements for a production order?
Note: There are 3 correct answers to this question.

  • A. Float before production
  • B. Transit time
  • C. Load time
  • D. Setup time
  • E. Queue time

Answer: A,D,E


NEW QUESTION # 34
What is the purpose of the pull list in material staging?

  • A. To control the flow of material from the production storage location to the central storage location
  • B. To control the flow of material from the supplier to the central storage location
  • C. To control the flow of material from the central storage location to the production storage location
  • D. To control the flow of material from the supplier to the production storage location

Answer: C


NEW QUESTION # 35
You want to trigger in-house production of a semi-finished material before a sales order for the corresponding finished good is received.
Which planning strategy supports the consumption of planned independent requirements by dependent requirements for the semi-finished material?

  • A. Planning with final assembly (40)
  • B. Production by lot size (30)
  • C. Assembly processing with production orders (82)
  • D. Planning at assembly level (70)

Answer: D


NEW QUESTION # 36
Under what circumstances can you change the material type for a material if stocks, reservations, or purchasing documents exist? Note: There are 2 correct answers to this question.

  • A. The same batch management level is used.
  • B. The same account category is used.
  • C. The quantity and value updates are the same.
  • D. The same base unit of measure is used.

Answer: C,D


NEW QUESTION # 37
What are the selection criteria of a bill of material (BOM) alternative?
Note: There are 2 correct answers to this question.

  • A. Date
  • B. Lot size
  • C. Material BOM usage
  • D. Change number

Answer: A,B


NEW QUESTION # 38
In SAP documentation for MRP in Advanced Planning, you read that the MRP creates new planned orders through infinite scheduling. What does this mean for the capacity requirements of the new planned order?

  • A. MRP creates the capacity requirements without considering existing load on the resources.
  • B. MRP automatically assigns the capacity requirements to resources with the earliest available capacity.
  • C. MRP automatically assigns the capacity requirements after the last scheduled operation for each resource.
  • D. MRP creates the capacity requirements on resources at the earliest possible production time.

Answer: A


NEW QUESTION # 39
Which of the following questions do you have to answer before you start creating a bill of material (BOM)? Note: There are 2 correct answers to this question.

  • A. Which base unit of measure must the BOM have?
  • B. When does the BOM need to become effective?
  • C. For which plant can the BOM be defined?
  • D. In which storage location is the BOM required?

Answer: B,C


NEW QUESTION # 40
When does the system trigger replenishment for a Kanban container?

  • A. When you set the container to Full
  • B. When you set the container to In transit
  • C. When you set the container to Waiting
  • D. When you set the container to Empty

Answer: D


NEW QUESTION # 41
In the context of the capacity scheduling table, how do you define a pacemaker work center?

  • A. By assigning it to the capacity scheduling table
  • B. By assigning it to the bottleneck operation
  • C. By assigning it to the production version
  • D. By assigning it to the first operation of a routing

Answer: C