[Feb 28, 2022] Updates Up to 365 days On Valid SIAMF Braindumps Best QualitySIAMF Exam Questions EXIN Test To Gain Brilliante Result EXIN SIAMF Exam Syllabus Topics: TopicDetailsTopic 1Explain SIAM roles and responsibilities, SIAM structural elements Outline the importance of security, the associated risks and mitigationsTopic 2Describe the challenges associated with measuring success and its mitigations [...]

[Feb 28, 2022] Updates Up to 365 days On Valid SIAMF Braindumps [Q19-Q35]

Share

[Feb 28, 2022] Updates Up to 365 days On Valid SIAMF Braindumps

Best QualitySIAMF Exam Questions EXIN Test To Gain Brilliante Result


EXIN SIAMF Exam Syllabus Topics:

TopicDetails
Topic 1
  • Explain SIAM roles and responsibilities, SIAM structural elements
  • Outline the importance of security, the associated risks and mitigations
Topic 2
  • Describe the challenges associated with measuring success and its mitigations
  • Distinguish between the different SIAM implementation key stages
Topic 3
  • Describe the importance of the level of control and ownership, the associated challenges and mitigations
  • Define the commercial challenges, the challenges with legacy contracts and their mitigations
Topic 4
  • Describe the technology practices of creating a tooling strategy
  • Outline the purpose and value of a SIAM approach
Topic 5
  • Describe the measurement practices of enabling and reporting on end-to-end services
  • Describe the people practices of managing cross functional teams

 

NEW QUESTION 19
What is a practice associated with creating a tooling strategy?

  • A. ease of adding and removing SLA's
  • B. ease of adding and removing business requirements
  • C. ease of adding and removing service providers
  • D. ease of adding and removing data dictionaries

Answer: C

 

NEW QUESTION 20
Which process records and manages service issues that are interrupting theavailability of a service?

  • A. problem management
  • B. incident management
  • C. change management
  • D. request fulfillment

Answer: B

 

NEW QUESTION 21
A customer organization has an internally sourcedservice integrator.
What is a responsibility of the customer organization's retained capabilities?

  • A. performing day to day management of service provision
  • B. managing end-to-end performance of the service providers
  • C. providing service communications
  • D. defining the roadmap for technology, data, and applications

Answer: D

 

NEW QUESTION 22
What is an objective of the Discovery and Strategy stage of theSIAM roadmap?

  • A. obtain full approval of the SIAM model
  • B. put in place and in use the new SIAM model
  • C. establish the SIAM transition project
  • D. complete the design of the SIAM model

Answer: C

 

NEW QUESTION 23
What is the earliest stage of the SIAM roadmap in which gaps between process activities need to be identified and addressed?

  • A. Discovery and Strategy
  • B. Plan and Build
  • C. Run and Improve
  • D. Implement

Answer: B

 

NEW QUESTION 24
What is a disadvantage of the hybrid service integrator structure?

  • A. Thecustomer can inadvertently develop a long term dependency on the service integration partner.
  • B. The high level of dependencyon the service integrator adds risks to continuity.
  • C. The service integrator might be perceived to be biased, even if this is not the case.
  • D. The customer can revert to an internally sourced solution if the service integration partner fails to live up to expectations.

Answer: B

 

NEW QUESTION 25
Which process ensures that service performance meets agreedrequirements?

  • A. service level management
  • B. project management
  • C. incident management
  • D. change management

Answer: A

 

NEW QUESTION 26
The development of an integrated process model is a critical part in the success of a SIAM implementation.
What approach should a service provider take when developing their process model for the SIAM implementation?

  • A. use the service integrator's processes
  • B. adapt and augment their own processes
  • C. use the customer organization's processes
  • D. use existing processes

Answer: B

 

NEW QUESTION 27
What is an objective of the Discovery and Strategy stage of the SIAM roadmap?

  • A. manage day to day service delivery
  • B. establish a governance framework
  • C. manage processes, teams, and tools
  • D. appoint the service integrator and provider

Answer: B

Explanation:
Explanation/Reference:

 

NEW QUESTION 28
Which process manages escalations regarding the performance of a service provider?

  • A. service level management
  • B. incident management
  • C. supplier management
  • D. business relationship management

Answer: C

 

NEW QUESTION 29
When an incident occurs,what approach should a service provider adopt in order to overcome the challenges of cross-functional teams?

  • A. fix first, argue later
  • B. Ishikawa approach
  • C. argue first, fix later
  • D. Root-cause analysis

Answer: A

 

NEW QUESTION 30
What is an activity of the Plan and Build stage of the SIAM roadmap?

  • A. appoint service providers
  • B. define the strategic objectives
  • C. performance management and improvement
  • D. selecting the implementation approach

Answer: A

 

NEW QUESTION 31
Which practice provides a way to structure data and information from service measurement, to support the practice for enabling and reporting on end-to-end services?

  • A. create a reporting framework
  • B. apply agile thinking
  • C. use qualitative and quantitative measures

Answer: A

 

NEW QUESTION 32
Within SIAM, what does not support effective management of cross-functional teams?

  • A. knowledge, data and information
  • B. clear goals and objectives
  • C. roles and responsibilities
  • D. world class toolset

Answer: D

 

NEW QUESTION 33
Which processes are strongly related to event management?

  • A. problem management, change and release management, and monitoring and measuring
  • B. monitoring and measuring, incident management, and availability management
  • C. business relationship management, change and release management, and incident management
  • D. portfolio management, business relationship management, and problem management

Answer: B

 

NEW QUESTION 34
An important DevOps concept is the incremental of new functionality, followed by user feedback before the next increment.
In a SIAM ecosystem, what should be put in place specifically to support this DevOps concept?

  • A. removal of waste from the process
  • B. automated test suites for the end-to-end service
  • C. trust the service providers and empower them to deliver their services without interference
  • D. integrated change advisory board

Answer: B

 

NEW QUESTION 35
......